Answer:
Direct labor cost= $520,000
Step-by-step explanation:
Giving the following information:
The budgeted production of Taurus, Inc. is 13,000 units per month. Each unit requires 30 minutes of direct labor to complete. The direct labor rate is $80 per hour.
First, we need to calculate the total direct labor hours:
Direct labor hours= 13,000*0.5= 6,500 hours
Now, we can calculate the direct labor cost:
Direct labor cost= 6,500*80= $520,000