Paul, a contractor, has a contract to build a new office building for Bill. The contract contains a provision requiring Paul to furnish a certificate of occupancy from the building inspector before Bill is required to pay. This provision is:
A. an express condition.
B. an implied-in-fact condition.
C. an implied-in-law condition.
D. a condition subsequent