Answer:
$1,188 unfavorable
Step-by-step explanation:
The computation of the total direct labor variance is shown below:
Total Labor Variance is
= Total standard cost - total actual cost
= (Standard hours × Standard rate) - (Actual hours × Actual rate)
= (980 units × 4.5 × $14) - ($62,928)
= 61,740 - $62,928
= $1,188 unfavorable
Since the actual cost is more than the standard cost which results into unfavorable variance