Answer:
11,303 Hrs
Step-by-step explanation:
Now here, we can use the learning curve formula, which is as under:
Y = a * X^ (log of learning rate / log 2)
Here
Y is the average time taken by each unit
a is the time taken by the first unit which is 25000 hrs
X is the number of units to be produced which is 16 unit (Including the first unit)
Learning Rate is given and is 82%
So by putting values we have:
Y = 25,000 hrs * 16 ^ (Log 0.82 / Log 2)
Y = 25,000 * 16^(-0.2863)
Y = 25,000 * 0.45212 = 11,303 Hrs