Many project managers like to use the Tracking table to update progress because it shows the currently scheduled task start and finish dates (the Update Tasks dialog box does not show the scheduled start and finish dates).A. TrueB. False

1 Answer

3 votes

Answer:

False

Step-by-step explanation:

It is incorrect