The target cost per iron= $83.25
Step-by-step explanation:
Profit Required = Required Investment * required rate of return
= $ 3,500,000*15%
= $ 525,000
Sales= 300000*85=$25,500,000.00
Less: profit required=$525,000.00
Cost= Sales- Profit
Cost=24,975,000.00
Per Unit Target Cost = Total Cost / Total Units
= $ 24,975,000/ 300,000
= $ 83.25