You were hired by a small business as the project manager of a project involving a market analysis. This project will determine whether the company goes ahead with the large scale manufacturing of a brand new product. The activities of the project are described below, with their respective durations:
ID Description Duration (2 weeks) Predecessor
A Survey designed 2 None
B Pilot 1 A
C Data collection 3 A
D Data Processing 1 B, C
E Analyze survey Results 2 D
F Analyze market trends 3 D
G Demographics 2 E
H Report and Presentation 2 F, G
Draw a project network with this information.