Answer:
The correct answer here is A)
Here is why.
Step-by-step explanation:
If it is not recognized in the current period, it may be misleading. A forecast is indicative that a budget has already taken place and that resources have been released.
So even though cost estimates at the end of the incumbent period may indicate that a loss will result once the contract is completed, under the Zero-Profit, Completed- contract and percentage-of-completion methods, the entire loss that is expected on the contract must be recognized in the current period.
Cost estimation in project management speaks to identifying taking cognizance of the cost and other resources needed to finish a project whose purview or extent is properly defined.
A good cost estimate must include a detailed Basis of Estimate (BOE) report that describes the assumptions, exclusions, inclusions, accuracy and other aspects that are needed to interpret the total project cost.
Cheers!