133k views
2 votes
The Master schedule input in to the MRP system is focused at different levels depending on the Process strategy. For a repetitive assemble-to-order process operation, the Master schedule is focused at: a. Finished product level b. Material input level c. Module level d. None of the levels listed here

1 Answer

1 vote

Answer:

The best answer is"A"

Finished product level

Step-by-step explanation:

The material requirement plan specifies the quantity and timing of planned order releases and inorder to have a continuous (make-to-stock) operations, the master production schedule must be focused in that finished product level.

User Pickles
by
8.1k points

Related questions

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.