Answer : D.) $162,500
Explanation :
Given the following projected annual production cost;
Unit-level material cost $ 3
Unit-level labor cost $ 2
Unit-level overhead $ 1
Batch-level cost (5,000 units per batch) $ 5,000
Product-level supervisory salaries $ 37,500
Allocated facility-level costs $ 20,000
Titak units required = 15,000
Unit level cost per unit = $(3+2+1) = $6
Total unit cost = 15,000 × $6 = $90,000
Total batch level cost = $5000 × 3 = $15,000
Product-level supervisory salaries = $37,500
Allocated facility-level cost = $20,000
Total relevant cost = $(90,000+15,000+37500+20000) = $162,500