144k views
4 votes
In the current year, Mitchell Manufacturing expected Job No. 13 to cost $600,000 of overhead, $650,000 of materials, and $400,000 of labor. Mitchell applied overhead based on direct labor cost. Actual production required an overhead cost of $420,000, $750,000 of materials used, and $300,000 of labor. All of the goods were completed. What amount was transferred from Work in Process to Finished Goods?

User Okazari
by
7.3k points

1 Answer

4 votes

Answer:

Multiple choices:

$1,670,000.

$1,500,000.

$1,650,000.

$1,470,000.

The correct option is $1,500,000

Step-by-step explanation:

The overhead is applied on the basis of direct labor cost as follows:

overhead allocation rate=$600,000/$400,000=1.5 times

Materials used $750,000

Labor cost $300,000

prime cost $1,050,000

overhead(direct labor cost*1.5)=300,000*1.5 $450,000

The amount of transferred finished goods from WIP $1,500,000

The correct option is B,$1,500,000

The option of $1,470,000 was computed by adding up all actual costs incurred without reference to the overhead allocation of 1.5

User Michalmuskala
by
8.8k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories