In December 2016, Custom Mfg. established its predetermined overhead rate for jobs produced during 2017 by using the following cost predictions: overhead costs, $680,000, and direct materials costs, $400,000. At year-end 2017, the company’s records show that actual overhead costs for the year are $897,200. Actual direct material cost had been assigned to jobs as follows.

Jobs completed and sold $ 420,000 Jobs in finished goods inventory 76,000 Jobs in work in process inventory 53,000 Total actual direct materials cost $ 549,000 Determine the predetermined overhead rate for 2017.

User Ege Rubak
by
5.1k points

1 Answer

0 votes

Answer:

POAR= 170% of the direct material cost.

Step-by-step explanation:

Step-by-step explanation:

The predetermined overhead absorption rate (POAR: The overhead absorption is a rate which is used to charge overheads to production units. Note that this rate is computed using estimated figures

The rate is computed as follows:

Predetermined overhead absorption rate

POAR

= (Budgeted overhead for the period/Budgeted direct material cost)× 100

= $680,000/400,00 × 100

= 170% of the direct material cost.