Your team has already created a WBS for the ABC product launch project. You are kicking off phase 2 of this project, which is the product development phase. Which of the following is an example of what might appear in the second level of your project’s WBS?

A. ABC product launch project.
B. Work package.
C. Project phases.
D. Activities.

User Dennisa
by
6.5k points

1 Answer

3 votes

Answer:

C. Project phases.

Step-by-step explanation:

Work Breakdown Structure (WBS) in project management is the laser-focused breakdown of a project into smaller components in order to make the project successful.

Project phases is an example of what might appear in the second level of your project’s Work Breakdown Structure (WBS).