Answer:
c. $1,610,000
Step-by-step explanation:
Eilert would recognize gross profit on the
building of:
Costs to date $17,710,000-Estimated cost of $38,500,000× Building $42,000,000-Estimated cost $38,500,000
Hence:
($17,710,000 ÷ $38,500,000) × $3,500,000
=0.46×$3,500,000
=$1,610,000
Therefore Eilert would report Construction in Process in the amount of:=$1,610,000