An assembly line with 30 activities is to be balanced. The total amount of time required for all 30 activities is 45 minutes. The line will operate for 420 minutes per day. Which of the following must be the cycle time to achieve an output rate of 300 units/day?a.0.80 minutesb.1.4 minutesc.2.4 minutesd.3.0 minutes

1 Answer

5 votes

Answer:

The needed cycle time must be 1.4 min

Step-by-step explanation:

Given:

Production time per day
t = 420 min

Desired unit of output per day
X = 300

Total activity
= 30

For finding cycle time,

From the formula of cycle time,


t' = (t)/(X)


t' = (420)/(300)


t ' = 1.4 min

Therefore, the needed cycle time must be 1.4 min