You want the system of inequalities that describes the Acme Class Ring Company's ring production, given production limits of up to 140 rings per day and 350 total man-hours. Each of the x VIP rings takes 5 man-hours, and each of the y SST rings takes 7 man-hours.
Constraints
There are two constraints—one on the number of rings, and one on the number of man-hours. Each of these gives rise to an inequality describing the company's ring production.
x + y ≤ 140 . . . . . constraint on the number of rings
5x +7y ≤ 350 . . . . . constraint on the number of man-hours
__
Additional comment
The constraint on man-hours means the constraint on production quantity will always be satisfied. The man-hour constraint means the company can produce at most 70 rings per day.