Answer:
1. $0.24 per unit
2. $0.20 per unit
Step-by-step explanation:
1. The computation of cost per equivalent unit of direct material is given below:-
Here, material is at the beginning, so it will equals to 100%. Now the equivalent units for material will be completed units + closing Work in progress
= 100,000 units
Conversion cost = (Units completed × 100%) + (Closing Work in progress × 80%)
= (0 × 100%) + (100,000 × 80%)
= 80,000 units (no unit is completed)
Equivalent cost per unit = Cost involved ÷ Equivalent units
= $24,000 ÷ 100,000 units
= $0.24 per unit
Conversion cost = Total conversion cost ÷ Conversion cost
= $16.000 ÷ 80,000 units
= $0.20 per unit