Answer:
$ 861
Step-by-step explanation:
We are given the total fixed overhead from which we can determine the fixed overhead rate and then sum it up with variable overhead rate. The total overhead rate is multiplied with the number of direct labor hours to get the applied overhead.
Meenach Corporation
Total fixed manufacturing overhead cost $74,000,
Predetermined fixed overhead rate= Fixed manufacturing overhead cost / No of direct labor Hours
Predetermined fixed overhead rate=$74,000/74,000=$ 1
Variable manufacturing overhead rate of $3.10 per direct labor-hour
Total Overhead Rate= 1+3.10= $ 4.10
Job X387 required 210 direct labor-hours
Total applied Overhead to Job X387= $ 4.10 * 210= $ 861