Answer:
Option B,$0 profit is the correct answer.
Step-by-step explanation:
Using the completed-contract method in contract costing implies that all the revenue as well as the associated contract costs are recognized at the end of the contract period.
Specifically,Gleason construction in the process of constructing ,hence no costs and revenue can be recognized ,they are deferred to the completion date of the contract.
The correct option based above explanation is B,$0 profit