Answer:
$68,800
Step-by-step explanation:
Data provided
direct material = $16,000
Direct labor = $24,000
Production overhead = 120%
The computation of total cost of Job #450 is shown below:-
Total cost = Direct material + Direct labor + Production overhead
= $16,000 + $24,000 + (120% × $24,000)
= $16,000 + $24,000 + $28,800
= $68,800