Answer:
Total Budgeted Direct Labor costs $ 35,515
Step-by-step explanation:
Computation of Direct labor Cost
Strike Turkey Total
Production Units 2,300 3,100 5,400
Cutting per bag hours 0.15 0.20
Sewing per bag hours 0.25 0.35
Total Cutting hours 345 620 965
Total Sewing hours 575 1,085 1,660
Cost per hour - Cutting $ 11 per hour
Cost per hour Sewing $ 15
Total labor costs Cutting department ($ 11 per hour 965 hours = $ 10,615
Total labor costs Sewing department ($ 15 per hour*1,660 hours = $ 24,900
Total Budgeted Direct Labor costs $ 35,515