Answer:
$1,475 Favorable
Step-by-step explanation:
The computation of labor rate variance is shown below:-
For computing the labor rate variance first we need to compute the Actual rate Per Hour
= Total Cost ÷ Actual Hours
= $54,575 ÷ 5,900
= $9.25
Now,
Labor Rate Variance = (Standard Rate - Actual Rate) × Actual Hours
= ($9.50 - $9.25) × 5,900
= $0.25 × 5,900
= $1,475 Favorable
So, for computing the labor rate variance we simply applied the above formula.