If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round Mean, Standard Deviation, z-value to 2 decimal places and Probability to 4 decimal places.) Path Mean Std. Dev. a-d-e-h 24.33 1.35 a-f-g 15.50 1.26 b-i-j-k 14.83 1.02 c-m-n-o 26.17 1.66 Probability ($1,000) .4099 Probability ($500)

User Telokis
by
8.4k points

1 Answer

3 votes

Answer:

Probability of finishing within 26 weeks of start and earning $ 1000 bonus = 46%

Probability of finishing within 27 weeks of start and earning $ 500 bonus = 69.23%

Explanation:

If the project is finished within 26 weeks of its start, the project manager will-example-1
User Peter Hudec
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories