Answer:
The correct answer is $5.12 and $190.
Step-by-step explanation:
According to the scenario, the given data are as follows:
Lowest direct labor hour = 80 direct labor hour
Lowest maintenance cost = $600
Highest direct labor hour = 500
Highest maintenance cost = $2,750
So, we can calculate the variable maintenance cost per unit by using following formula:
Variable maintenance cost = (Highest cost - Lowest cost) ÷ (Highest direct labor hour - lowest direct labor hour)
= ($2,750 - $600 ) ÷ ( 500 - 80)
= $2,150 ÷ 420
= $5.12
Now we can calculate the total fixed maintenance cost by using following formula:
Total cost = Variable cost + Fixed cost
$2,750 = ( 500 × $5.12) + Fixed cost
Fixed cost = $2,750 - $2,560
= $190