152k views
0 votes
What are defects in the design and organization of processes and systems, things like poor equipment design, inadequate training, or insufficient resources that are often unrecognized or just become accepted aspects of the work, and their effects are delayed called:_________.

2 Answers

3 votes

Answer:

Latent conditions

Step-by-step explanation:

Latent conditions are defects in the design and organization of processes and systems; things like poor equipment design, inadequate training, or insufficient resources. These errors are often unrecognized or just become accepted aspects of the work, and their effects are delayed.

User Tom Womack
by
5.4k points
2 votes

Answer:

LATENT CONDITIONS

Step-by-step explanation:

The defects in the design and organization of processes and systems, things like poor equipment design, inadequate training, or insufficient resources that are often unrecognized or just become accepted aspects of the work, and their effects are delayed called LATENT CONDITIONS

Latent conditions are physical conditions on, underlying or adjacent to the site that could not be identified by the contractor by reasonable observations or investigations of the site or the site information provided in the tender documentation at the time that the tender for the works was being prepared.

User Rollin
by
5.6k points