Answer:
The answer is $ 965. $965 should be assigned to the job
Step-by-step explanation:
Since we're given the material cost we need to calculate the labour cost and the overhead cost. The hours worked are given. Thus multiplying the hours worked by the labour rate and overhead rate we can determine these cost. If we total the labour rate and the overhead rate we get a rate of $ 30. 30 x 20 = 600. Thus the total is $ 965.