Answer:
$7.2 and $10
Step-by-step explanation:
The computation of the standard cost per unit for direct material and for direct labor is shown below:
Direct materials standard cost per unit is
= 3 lbs × 2.4
= $7.2
And, Direct labor standard cost per unit is
= $15 × 40 ÷ 60
= $10
All the other information which is mentioned in the question is not relevant. Hence ignored it