Answer:
Direct labor budget:
Total hours= 123,690 hours
Total cost= $3,339,630
Step-by-step explanation:
Giving the following information:
Direct labor per unit= 3.1 hour
Direct labor rate= $27
Production budget for June:
Sales= 40,000 units
Ending inventory= 100 units
Beginning inventory= (200) units
Total production= 39,900 units
Now, we can determine the total number of hours required and the total cost:
Direct labor budget:
Total hours= 39,900*3.1= 123,690 hours
Total cost= 123,690*27= $3,339,630