The capacity requirement for a week at Work Center A is 151 hours
Step-by-step explanation:
Labor hours per unit of component in automobile factory = 0.75 hours
Setup time required in Work Center A = 1 hour
The planned order size for a week = 200 units.
Capacity = Setup time + [Processing time × Order size].
- Capacity = 1 + (0.75 * 200)
- Capacity = 1 + 150
- Capacity = 151 hours