A generator bus (with a 1.0 p.u. voltage) supplies a 200 MW, 80 Mvar load through a lossless transmission line with pu (100 MVA base) impedance of j0.1 and no line charging. Starting with an initial voltage guess of 1.0∡0°, iterate until converged using the Newton-Rapson power flow method. For convergence criteria, use a maximum power flow mismatch of 0.1 MVA.

User Carrein
by
3.2k points

1 Answer

5 votes

Answer:

Step-by-step explanation:

find attached solution

A generator bus (with a 1.0 p.u. voltage) supplies a 200 MW, 80 Mvar load through-example-1
A generator bus (with a 1.0 p.u. voltage) supplies a 200 MW, 80 Mvar load through-example-2
A generator bus (with a 1.0 p.u. voltage) supplies a 200 MW, 80 Mvar load through-example-3
A generator bus (with a 1.0 p.u. voltage) supplies a 200 MW, 80 Mvar load through-example-4
A generator bus (with a 1.0 p.u. voltage) supplies a 200 MW, 80 Mvar load through-example-5