Answer:
Fixed Cost = 100 ; Average Cost = Q - 10 + 100/Q
Average Cost Minimising Quantity = 10
Step-by-step explanation:
Total Cost is the total production expenditure on all factors of productions, for all output quantities.
Total Cost (TC) is sum of Total Fixed Cost ( TFC) , Total Variable Cost (TVC)
- Variable Cost is the cost incurred on variable factors of production. It varies directly with production quantity, is 0 at 0 production level.
- Fixed Cost is the cost incurred on fixed factors of production. It is constant at all production quantity, not 0 even at 0 production level.
So, TFC is the constant component of total cost function
TC Function = Q^2-10Q+100
TFC = Constant numeral = 100
Average Total Cost is the total cost per unit of output
ATC = TC / Q
(Q^2-10Q+100) / Q
= Q - 10 + 100/Q
ATC minimised : per first derivative rule
dTC / dQ = 1 - 100/Q^2
1 - 100/Q^2 = 0
1 = 100 / Q^2
Q^2 = 100
Q = 10