reventive action ____________. a. realigns the performance of the project work with the project management plan b. seeks to ensure the future performance of the project work is aligned with the project management plan

1 Answer

4 votes

Answer:

The correct answer is letter "B": seeks to ensure the future performance of the project work is aligned with the project management plan.

Step-by-step explanation:

Preventive actions are defined as those that aim to mitigate risks inherent in the operations of a business. Preventive actions lead to entities creating contingency plans that allow them to have certain strategies in front of unexpected situations that could harm the firm's operations.

The project risk management plan is the reference that prevention actions take at the moment of recognizing the set of activities that should be followed to ensure the optimal future performance of a project.

User Wowo Ot