Answer:
90.5% and 79.2%
Step-by-step explanation:
Given that
Design capacity = 1200
Effective capacity = 1050
Employees trained/usage/actual output = 950
Therefore,
Efficiency = actual output/effective capacity × 100
= (950/1050) × 100
= 0.9047 × 100
= 90.47%
= 90.5%
For the Utilization
= actual output /design capacity × 100
= (950/1200) × 100
= 0.7916 × 100
= 79.16%
= 79.2%