Answer:
Direct material= $11,800
Step-by-step explanation:
Giving the following information:
Total cost= $66,200
Job No. 173 has been charged with manufacturing overhead costs of $20,400. Denver allocates manufacturing overhead costs at a rate of 60% of direct labor cost.
First, we need to determine the direct labor cost.
Direct labor cost= allocated overhead/0.6
Direct labor cost= 20,400/0.6= 34,000
Now, we can calculate the direct material cost:
Direct material= total cost - direct labor - allocated overhead
Direct material= 66,200 - 54,400
Direct material= 11,800