118k views
5 votes
Pouch Corporation is working on its direct labor budget for the next two months. Each unit of output requires 0.80 direct labor-hours. The direct labor rate is $11.10 per direct labor-hour. The production budget calls for producing 3,800 units in June and 3,600 units in July. If the direct labor work force is fully adjusted to the total direct labor-hours needed each month, what would be the total combined direct labor cost for the two months

1 Answer

7 votes

Answer:

June= $33,744

July= $31,968

Total= $65,712

Step-by-step explanation:

Giving the following information:

Each unit of output requires 0.80 direct labor-hours. The direct labor rate is $11.10 per direct labor-hour. The production budget calls for producing 3,800 units in June and 3,600 units in July.

First, we need to determine the total number of hours required:

June= 3,800*0.8= 3,040 hours

July= 3,600*0.8= 2,880 hours

Now, we can calculate the total cost:

June= 3,040*11.1= $33,744

July= 2,880*11.1= $31,968

Total= $65,712

User Jason Kulatunga
by
8.6k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories