Contribution per unit of scare resource (in hour) = $24 per hour
Step-by-step explanation:
The question falls under the limiting factor analysis
When a business is faced with a problem of shortage of a resource which can be used to produced more than one product type, to maximize the use of the resource , the business should allocate it for production purpose in such a way that it maximizes the contribution per unit of the scare resource.
Therefore Santario Company should allocate the machine hours to maximize the contribution per unit of machine hour.
Contribution per unit of scare resource is determine as follows:
Contribution per unit of scare resource for Model K-3
Contribution per unit of Model K-3 = $6
Machine time per unit = 15 minutes
Contribution per unit of scare resource in minutes
=Contribution per unit/Machine time per unit
= 46/15 minutes
= $0.4 per minute
Contribution per unit of scare resource (in hour)
$0.4 per minutes× 60
= $24 per hour