61.3k views
1 vote
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of three weeks. Lot-for-lot lot sizing is used for Items A, D, and E; lots of size 50, 100, and 50 are used for Items B, C, and F, respectively. Items A, C, D, and E have on-hand (beginning) inventories of 20, 50, 100, and 10, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in Week 1, 100 units of C in Week 1, and 100 units of D in Week 3; there are no other scheduled receipts.

Note: To simplify data handling to include the receipt of orders that have actually been placed in previous periods, the following six-level scheme can be used. (A number of different techniques are used in practice, but the important issue is to keep track of what is on hand, what is expected to arrive, what is needed, and what size orders should be placed.)

If 50 units of A are required in Week 10, use the low-level-coded bill of materials (product structure tree) to find the necessary planned order releases for all components.

User Nital
by
5.8k points

1 Answer

4 votes

Answer:

Use the following method to complete the MRP tables:

Gross requirements of period-j (G_j) = Σ_k n_k* (PORelease_j of the parent-k) where nk = number of units of the item used in 1 unit of its parent-k

Scheduled receipts in period-j (SR_j): to be entered manually

Projected on-hand in period-j (I_j) = Max.(0, I_{j-1} + SR_j + POReceipt_j - G_j)

Net requirements in period-j (N_j) = Max.(0, G_j - SR_j - I_{j-1})

Planned order receipts of period-j (POReceipt_j): to be entered manually when there is a positive net requirement based on the lot size rule.

Planned order release of period-j (PORelease_j) = POReceipt_{j+L}

Step-by-step explanation:

One unit of A is made of one unit of B and one unit of C. B is made of four units-example-1
One unit of A is made of one unit of B and one unit of C. B is made of four units-example-2
One unit of A is made of one unit of B and one unit of C. B is made of four units-example-3
One unit of A is made of one unit of B and one unit of C. B is made of four units-example-4
User Rishit
by
5.8k points