Answer:
$34.8 million
Step-by-step explanation:
Below are types of cost that Jenny, Inc. bears:
1) Investment (Six years ago) = $8,5 million (This is referred as sunk cost - which was already incurred and impossible to be recovered.)
2) Current value (Price today) = $11.3 million (This is the opportunity cost if Kenny does not sell the land but build the manufacturing plant.)
3) Plant cost = $22.5 million
4) Grading cost = $1 million
We have, the initial fixed asset investment = Plant cost + Grading cost = 22.5 + 1 = $23.5 million
The cash flow amount to use as the initial investment in fixed assets to evaluate the project would be the sum of the opportunity cost of project anf the initial fixed investment.
=> Cash flow = 11.3 + 23.5 = $34.8 million