Answer:
$792,960
Step-by-step explanation:
Data provided
Number of pods = 23,600
Direct labor hours = 3
Direct Labor Rate per hour = $11.20
The computation of Budgeted direct labor costs is shown below:-
Budgeted Direct labor Cost = Number of pods × Direct Labor Hours required per pod × Direct Labor Rate per hour
Budgeted Direct labor Cost = 23,600 × 3 × $11.20
= $792,960