Lean systems try to:

A. Produce product in anticipation of demand.
B. Maximize the value added by each of their activities.
C. Organize production in large batches to maximize the number of setups.
D. Expand the labor content in all processes.

User Eli Blokh
by
3.3k points

1 Answer

6 votes

Answer:

B. Maximize the value added by each of their activities.

Step-by-step explanation:

Lean systems are business systems whereby lean principles are holistically applied to the way they plan, organize, direct, control and prioritize work. The lean system is centered upon the customer as it tries to understand what value the customer assigns to products and services. It looks to maximize the value added by each of its activities by removing waste and delays from them. In summary, it maximizes customers' value.