You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 15 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 15 working days. Question: Do you expect to receive a bonus or penalty? How much do you expect to be given a bonus or penalty?

1 Answer

1 vote

Answer:

A) I expect to receive a bonus

B) I expect to get a $500 bonus by finishing within 15 working days.