Answer: -$2,350
Step-by-step explanation:
First we will calculate the labour costs of the product as,
Standard labour overheads required,
= 2,500*6
= $15,000
Using the above figure we will then calculate the Standard Overhead Cost as,
Standard overhead cost
= 4.9* 15,000 hours
= $73,500
But the Actual overhead cost = $71,150
The Variance is calculated as,
= standard overhead cost - actual overhead cost
= 73,500 - 71,150
= $2,350 Favorable.
= -$2,350
If you need any clarification do react or comment.