165k views
3 votes
Bay City Construction, Inc., a contractor, asks Cool Electric, a subcontractor, to provide certain services. Nothing is said about payment. Cool provides the services, but Bay City refuses to pay. In Cool’s suit to recover, the chief issue is most likely to be whether these parties had​:

A. a formal contract
B. an express contract
C. an implied contract
D. a voidable contract

1 Answer

2 votes

Answer:

C. an implied contract

Step-by-step explanation:

Based on the scenario being described it can be said that the chief issue is most likely to be whether these parties had​ an implied contract. This type of contract refers to when two parties have an agreement but there is no written contract existing regarding this agreement, instead the law enforces the contract and makes sure that the details are fair to both parties.

User Zorgmorduk
by
4.4k points