Answer:
Total cost = $236.929
+) Labor charges = $100.065
+) Cost of parts = $85.54
+) Material loading changes = $51.324
Step-by-step explanation:
First, we need to determine the hourly rate of labor in Verde Appliance Repair shop.
+) Total cost of Verde Appliance Repair Shop in a year is:
Total Cost = Repair-technicians' wages + Fringe Benefits + Overhead = 111,188 + 27,852 + 47,388 = $186,428
+) As the total labor hours are 4,400
=> Cost per hour = Total Cost ÷ Total Labor Hours = $186,428 ÷ 4,400 = $42.37
+) The hourly labor rate = Cost per hour + Profit margin = 42.37 + 24.34 = $66.71
The bill for the job if Verde repairs a dishwasher would include:
+) Labor charges = Hours x Hourly labor rate = 1.5 x 66.71 = $100.065
+) Cost of parts = $85.54
+) Material loading changes = 60% x Cost of parts = 0.6 x 85.54 = $51.324
=> Total costs = Labor charges + Cost of parts + Material loading changes
=> Total costs = 100.065 + 85.54 + 51.324 = $236.929