Answer:
Total labour budget for the quarter = $553,950
Step-by-step explanation:
Direct labor cost budget is prepared using the production budget.
It is prepared as follows:
Direct labour budget = budgeted labour hours × labour cost per hour
Budgeted labour hours = Budgeted production unit × labour hours per unit
Budgeted labour hours:
Deluxe - (1,000+1,100+980) × 2.25 hours = 6,160 hours
Standard- (5000 × 3) × 2 hrs = 30,000 hours
Total labor hours = 30,000 +6,160 = 36,930 hours
Total labor budget for the quarter
= 36,930 hours × $15 = $553,950
Total labor budget for the quarter =$553,950