Answer:
The correct answer is A.
Step-by-step explanation:
Giving the following information:
Manufacturing overhead costs $30,000
Machine-hours= 100,000
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 30,000/100,000= $0.3 per machine hour.