Answer:
The minimum cost production lot size = 2447.75
Step-by-step explanation:
Given
D = Demand = 7,800 copies.
C = Setup costs = $135 per setup.
A = Cost = $13.5.
R = Holding Cost Annual Rate = 17%
P = Production volume = 26,000 copies.
W = Working days = 250 per year
L = Lead time for a production run = 14 days
First we calculate the usage rate.
The usage rate = Annual rate of demand ÷ Working days
Usage Rate = 7500 ÷ 250 = 30 units daily
Then we calculate the production units
Production (P) = Annual Production Volume ÷ Working days
P = 26000 ÷ 250 = 104 units daily
Then we calculate the cost production lot size
This is calculated by
Cost production lot size = √(2DC)/√(1 - (D/P)R * A)
By substituton
Cost Production = √(2 * 7500 * 135)/√(1 - (7500/26000) * 0.17 * 13.5)
Cost Production = 2447.746953702503
Hence, the minimum cost production lot size = 2447.75 --- Approximately