Answer:
the cost to be assigned to the building is $288,000
Step-by-step explanation:
The Costs of Land, Building and Equipment have to be determined separately due to the fact that their usage is different and hence depreciation charges are different.
The Appraisal value is used to apportion the cost of $450,000 to the Land, Building and Equipment as follows :
PPE Item Appraised Value
Land $100,000
Building $320,000
Equipment $80,000
Total $500,000
Apportionment of Cost to Building :
Building = $320,000/ $500,000× $450,000
= $288,000