A critical first step in the initiating phase of a project is to conduct a needs analysis, which:____________.A. identifies the planned dates for performing tasks and meeting goals defined in a project plan. B. identifies the goals and tasks of a project, and the work required to complete them. C. identifies the requirements for each project task to ensure that the project objectives are met. D. identifies the problems or desires that the project must resolve or address.

User Salix Alba
by
5.3k points

2 Answers

5 votes

Answer:

D. identifies the problems or desires that the project must resolve or address.

Step-by-step explanation:

A critical first step in the initiating phase of a project is to conduct a needs analysis, which identifies the problems or desires that the project must resolve or address.

To successfully carry out a project, the manager should first of all, critically identify the problems or desires that the project must resolve or address. It's basically seeking a solution to the problem.

Thus, answering the question of "what purpose is the project serving"

User Billc
by
4.2k points
3 votes

Answer: D. identifies the problems or desires that the project must resolve or address.

Step-by-step explanation:

A critical first step in the initiating phase of a project is to conduct a needs analysis, which: identifies the problems or desires that the project must resolve or address.

The product must perform to provide the functionality expected, solve the identified problem, and deliver the benefit and value wanted.