Answer:
For Machine Setup:
Overhead=$80 per setup
For Machining:
Overhead=$13 per machine hours
For inspections:
Overhead=$32 per inspections
Step-by-step explanation:
Given Data:
Overhead cost for machine setups=$80,000
Overhead cost for machining=$162,500
Overhead cost for inspections=$28,000
Expected annual use in machine setups=1,000 setups
Expected annual use in machining=12,500 machine hours
Expected annual use in inspections=875 inspections.
Required:
Overhead rate for each activity=?
Solution:
For Machine Setup:
Overhead=

Overhead=

Overhead=$80 per setup
For Machining:
Overhead=

Overhead=

Overhead=$13 per machine hours
For inspections:
Overhead=

Overhead=

Overhead=$32 per inspections